Parking garage for F&M Bank Arena reaches next stage, projected to open by June 2025

Parking garage for F&M Bank Arena reaches next stage, projected to open by June 2025

Land is excavated for a new parking garage for the F&M Bank Arena at First and College Streets, next to Riverview Inn, in background, on July 9, 2024. (Chris Smith) Photo: Clarksville Now


CLARKSVILLE, TN (CLARKSVILLE NOW) – The 526-space parking garage for the F&M Bank Arena took another step forward Tuesday morning as the Clarksville-Montgomery County Industrial Development Board approved a guaranteed maximum price for the project.

The guaranteed maximum price for construction has come in under its $18.3 million budget at $17.5 million. The total budget for the project is just over $22 million. That will be paid for by a $14 million grant from the State of Tennessee, with Montgomery County Government covering the remainder. The IDB will own the garage, and will enter into a lease with a private company to manage it.

The board also heard an update Tuesday from the contractor on where things stand, with excavation mostly finished and foundation work coming next. Jordan Wyman with Commonwealth Development Group Inc. told the IDB they expect to have the foundations laid by the end of October. The precast forms should arrive in early November.

Economic Development Council CEO Buck Dellinger said that if those schedules are met, pending any delays for weather or other issues, the garage is expected to open by June 2025.

Dellinger said the planned Riverview Square retail development can’t start construction until space in the garage opens. Because the retail development will be built in the existing Riverview Inn/DoubleTree By Hilton parking lot, the new garage will have to absorb hotel parking before the existing lot is closed for construction.

City parking garage

The new City of Clarksville parking garage nearing completion at First and Commerce Streets, on July 9, 2024. (Chris Smith)

Meanwhile, the City of Clarksville is nearing completion of a new 587-space parking garage at First and Commerce Streets, connected to the existing Cumberland Parking Garage. It will include a pedestrian bridge from the Second Street level to Franklin Street, immediately adjacent to the planned Performing Arts Center.

Erection of the precast building components is complete. City Project Manager John Hilborn said Tuesday in a statement to Clarksville Now, “We anticipate opening the new parking garage on a specific date still to be determined in late August, assuming there are no unexpected weather, or other project-related delays.”

Clarification: The article has been updated to say the GMP came in under its $18.3 million budget at $17.5 million. The total budget is just over $22 million.

DON’T MISS A STORY: Sign up for the free daily Clarksville Now email newsletter

Latest Headlines

Archery range. (Shutterstock)

yesterday in Business, News

Indoor archery range, hunting supply store proposed on Dover Road, rezoning requested

More than 5 acres on the southern side of Dover Road have been requested for rezoning for an archery range where hunting supplies would also be sold.

Clockwise from top left, school bus crash, zinc plant, Checkers, DUI homicide case.

yesterday in News

News in Clarksville: School bus crash, Project Crucible, DUI death verdict and other top stories this week

Here’s a look at the top local news stories from Clarksville Now this week, including the aftermath of the fatal school bus crash, updates on the zinc plant project, and a DUI homicide verdict.

A proposed redevelopment of Frosty Morn for senior housing (Contributed, City of Clarksville)

Friday in News

Affordable senior housing proposed for Frosty Morn redevelopment, with 65 units

A special session meeting has been scheduled for the City Council to discuss a lease agreement for the development of affordable senior housing at Frosty Morn.

Friday in News

Family of girl killed in school bus crash files lawsuit against CMCSS, bus driver

The family of one of the girls killed in the Kenwood Middle School bus crash is filing a lawsuit against the Clarksville-Montgomery County School System.

Rustom Khouri addressing the Clarksville City Council on April 2, 2026. (Christian Brown)

Friday in News

‘I know it’s been a long road’: City Council OKs rezoning for new, 4-story VA Clinic

The Clarksville City Council unanimously approved the first reading of a 61-acre site rezone, which was recently selected as the location for Clarksville’s new VA Clinic.

Latest Headlines

2 days ago in National, Trending

US employers added a surprisingly strong 178,000 jobs last month, rebounding from a weak February

American employers added a surprisingly strong 178,000 new jobs last month, rebounding from a dismal February. And the unemployment...

2 days ago in National, Trending

The Latest: US and Israel are trying to rescue fighter jet crew in Iran, Israeli source says

The U.S. military launched a rescue operation Friday after Iranian state media reported that an American fighter jet went down and at least...

4 days ago in Entertainment, National, Trending

The Latest: Artemis II fully fueled for NASA’s historic return to the moon

NASA's launch team has loaded more than 700,000 gallons of fuel into the 32-story Space Launch System rocket, setting the stage for the Artemis II mission crew members to board...

4 days ago in Entertainment, Music

Megan Thee Stallion takes 2 Broadway shows off after illness during ‘Moulin Rouge!’

Megan Thee Stallion was rushed to the hospital after "feeling very ill" while onstage on Broadway in "Moulin Rouge! The Musical." She later took to social media to explain...

4 days ago in Entertainment, Music

Bruce Springsteen brings ‘Streets of Minneapolis’ home as he launches US tour with ‘War’

Bruce Springsteen was in a defiant but upbeat mood as he returned Tuesday night to the "Streets of Minneapolis" to launch his latest...